Valuers set the value of each compensation case, line by line: every tree, crop, building component and the land. The dictionary rate is shown beside each line as a guide only; the figure is yours, and no reason is needed for it. Every save is kept as a version. You can read every record; you change only the valuation.

Default role: Valuer Key permissions: comp.valuate evidence.upload data.export

Find cases waiting for you

  1. Open Compensation cases.
  2. Set the Status filter to Pending valuation. Bookmark the page: the filter is kept in the address.
  3. Narrow by project, LGA, ward, type or Scope if you work one location or one kind of item.

Each case has a number such as COMP-KSR-2026-01-0001 and a scope: what it pays for. A property can have several cases, for example the land as a 30% allocation and the buildings and trees in cash. Cases only open once the property and claimant data are complete, so the boundary, the items and the photos are always there to work from: open the case, then the property link under Property & survey.

Value the case on its worksheet

Open the case and its Valuation tab. Each line of the case is a row, grouped as Land · Buildings and structures · Economic trees · Crops · Other.

ColumnWhat it is
QtyThe quantity captured on the property (land: hectares).
Valuer qtyThe quantity you confirmed on site, if it differs. Blank keeps the captured quantity.
Valuer rateYour rate. The line is worth your rate × the quantity.
AmountThe line’s value. With a rate it is worked out; without one, type a lump sum for the line.

Under each item a grey line reads Guide: ₦… per unit (dictionary, for reference only): the dictionary rate when the case opened. It is helper text and nothing more. No figure is ever filled in from it, it is never added up into an amount, and you may value the line at whatever you judge right. Only valuers and administrators see dictionary rates.

  1. For the land (cases paying for the land), choose its zone: the guide under the line shows that zone’s rate per hectare.
  2. Type your figure for each line. Enter moves down the column, Tab across. A line worth nothing gets 0.
  3. Something the property’s items don’t cover (a disturbance allowance, loss of income)? Click Add another amount, name it and give the amount.
  4. An adjustment (+/−) on top of the lines needs a reason.
  5. Click Save version N. The figures are kept as version N; nothing earlier is overwritten. Add a note for the version if useful (for example “after the site visit”).
Rates

The guide rates come from the dictionaries under Administration › Dictionaries, which administrators keep to the approved KADGIS schedule (trees, crops and bare land from the 2017 Land Use Regulations). See the Administrator guide.

AI help on the worksheet

When your organisation has switched it on, AI help under the worksheet offers:

No claimant’s name or number is sent: only item names, quantities and figures.

Where the four-eyes rule is on (Administration › Rules), you cannot approve a case whose current valuation you saved: a colleague does.

Versions

Under the worksheet, Versions lists every save: its value, how many lines changed, who and when. View opens a version as it was. Tick two and click Compare the two ticked to see the lines side by side, changed ones highlighted. The minute sheet records each save (“Valued at ₦4,620,000 (version 2; 3 lines changed)”).

Working offline in Excel

Mark the case as Valuated

  1. When every line has a figure, click Save and mark as Valuated on the worksheet — or the amber Mark as Valuated…, which shows the assessed value for you to confirm.
  2. A line without a figure stops it: “2 lines have no value — enter a value or ₦0”.
  3. 30% land case: check the land area acquired (m²); the system works out the 30% allocated back to the claimant.

The case moves to Valuated and appears in Finance’s list of cases awaiting approval.

Several cases at Pending valuation whose worksheets are complete? Tick them in the register and click Move on to the next step…. Each moves on with its own value; a case with lines still to value stays and is named in the message.

Attach the valuation report

  1. In the case, open the Evidence tab and click Attach document.
  2. Valuation report is already chosen as the kind of document. Add a short description.
  3. Choose the file (PDF or a photo; up to 15 MB) and click Attach.

Made a mistake?

Before approval, change the worksheet and save again: a new version. After approval, only someone who can correct recorded values (comp.correct) can change the valuation; saving it sends the case back to Valuated to be approved again, and the minute shows the old and new value. Once a cheque is issued the valuation no longer changes; if more is owed, open a supplementary case on the same property.